Coal Ministry asks Reliance Power to cut production from Sasan’s coal mines

The Ministry of Coal has asked Reliance Power Ltd to revise the production plan from two mines allocated to the Sasan ultra mega power project to 16 million tonne per annum and present a new mining plan for the same.

The mining plan for the two mines – Moher and Moher Amlohri Extn – is currently 20 million tonne per annum. Production has already started from these mines.

In a letter to Sasan Power Ltd, the Coal Ministry said, “Sasan Power Ltd is required to revise the mining plan of Moher and Moher Amlohri coal blocks from the preset 20 million tonne per annum to 16 million tonne per annum mine capacity so as to conform to the coal requirement of 16 million tonne per annum for the Sasan UMPP, being the specified end use plant.”

Continue reading

Share

Amit Antil

After doing Power Management (MBA) from National Power Training Institute (NPTI), Amit Antil is now presently working with Today Green Energy Pvt. Ltd. and looking after business development activities for Solar. Earlier he was associated with leading power trading company Global Energy for 3 years. He has a sound knowledge about bidding, power trading, open access, REC trading, Govt. Liaisoning, Contract Negotiation, Power Purchase Agreement.

You may also like...

Leave a Reply

Your email address will not be published. Required fields are marked *


*